This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartApr 2028
CompletionMay 2029
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B18077
Asset typeWater - Distribution Sys - Distribution
Community areaSOUTHEASTERN SAN DIEGO, MID-CITY:CITY HEIGHTS, ENCANTO NEIGHBORHOODS, UPTOWN, MID-CITY:NORMAL HEIGHTS, NORTH PARK, NAVAJO
ContactPublic Information Line
Contact phone6195334207
Council district(s)8, 3, 7, 9, 4
DescriptionReplace approximately 448-LF (0.09 miles) of existing Cast Iron (CI) and 2732-LF (0.52 miles) of existing Asbestos Cement (AC) water mains; install approximately 1,150-LF (0.22 miles) of new 16-inch P
Map pieces13
Source last edited2020-04-21

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-09-11Majorcompletion date slipped ~1.7 years
2026-08-07Routinestart date slipped ~5 weeks