Construction Project Update

Water Group 525E

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartApr 2029
CompletionDec 2030
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B00131
Asset typeWater - Distribution Sys - Distribution
Community areaBARRIO LOGAN, DOWNTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)8, 3
DescriptionReplacement of approx. 5,350 linear feet (1.01 miles) of existing 6, 8, 10, 12, 16, and 24-inch asbestos cement (AC), cast iron (CI), cement mortar lined and coated steel (CMLCS), and reinforced concr
Map pieces30
Source last edited2026-02-10

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-07Routinestart date slipped ~2 weeks