Construction Project Update

Water Group 525C

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartApr 2029
CompletionDec 2030
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B00032
Asset typeWater - Distribution Sys - Distribution
Community areaBARRIO LOGAN, DOWNTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)8
DescriptionReplacement of approx. 3,548 linear feet (0.67 miles) of existing 6 & 16-inch asbestos cement (AC) and cast iron (CI) water mains. Construction of approx. 1,641 linear feet (0.31 miles) of new 12 and
Map pieces30
Source last edited2021-03-15

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-07Routinestart date slipped ~2 weeks