Traffic Signal Mods Grp 20-01

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusConstruction
Stageactive
StartMay 2025
CompletionOct 2026
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B20075
Asset typeTrans - Signals - Traffic Signals
Community areaENCANTO NEIGHBORHOODS, DOWNTOWN, MIRA MESA
ContactPublic Information Line
Contact phone6195334207
Council district(s)6, 3, 4
DescriptionThis project proposes to modify and upgrade traffic signals at three intersections: 1) 14th St @ Broadway: Modify signals for southbound traffic, install service point, pedestrian countdown timers, cu
Map pieces3
Source last edited2024-05-10

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinecompletion date slipped ~4 weeks
2026-09-11Routinecompletion date slipped ~3 weeks