Stockton Improv 1 (S)
San Diego · San Diego CIP
This city’s feed last changed on 2026-10-16. We check every morning.
| Status | Design |
|---|---|
| Stage | design |
| Start | May 2030 |
| Completion | Nov 2031 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:B20028 |
| Asset type | Wastewater - Collection Sys - Main |
| Community area | SOUTHEASTERN SAN DIEGO |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 8, 9 |
| Description | Replace 14,649 linear feet (LF) (2.77 miles) of existing vitrified clay (VC), install 2,256 LF (0.43 miles) of new sewer , and abandon 3,582 LF (0.68 miles) of existing vitrified VC, including associa |
| Map pieces | 36 |
| Source last edited | 2021-06-16 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-08-07 | Routine | start date nudged 4 day(s) |