Construction Project Update

SEWER GROUP 828

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartJul 2030
CompletionJan 2032
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B00434
Asset typeWastewater - Collection Sys - Main
Community areaNORTH PARK, BALBOA PARK
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionReplace approximately 8,748-LF (1.66 miles) of existing VC, PVC, CP sewer main.
Map pieces8
Source last edited2019-11-25

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinecompletion date slipped ~1.1 years
2026-09-11Majorcompletion date slipped ~1.0 years