Sewer & AC Water Group 1055 (W)

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartFeb 2028
CompletionNov 2029
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B18115
Asset typeWater - Distribution Sys - Distribution
Community areaDOWNTOWN, GREATER GOLDEN HILL
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionReplace approximately 6,136 linear feet (LF) (1.16 miles) of existing 6, 8, 12 and 16-inch diameter asbestos cement (AC) and Ductile Iron (DI) water pipes with 8, 12, and 16-inch Polyvinyl Chloride (P
Map pieces15
Source last edited2022-12-06

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinestart date moved earlier (2030-09-26 -> 2028-02-28)
2026-08-07Routinestart date nudged 1 day(s)