| Status | Design |
|---|---|
| Stage | design |
| Start | Apr 2027 |
| Completion | Sep 2030 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:L24000.2 |
| Asset type | Bldg - MWWD - Pump Stations |
| Community area | RESERVE AREA-Not a community plan, RESERVE AREA-Not a community plan, RESERVE AREA-Not a community plan, RESERVE AREA-Not a community plan, RESERVE AREA-Not a community plan |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 2 |
| Description | Repair liner and concrete in influent channel, replace corroded top supports for mechanical screens 1 through 4, rehab wet well #1 and #2, repair cooling tower pads, pipes, and pipe supports. Rehab 7 |
| Map pieces | 1 |
| Source last edited | 2024-05-10 |