Construction Project Update

Old Town Improv 1 (P)

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusConstruction
Stageactive
StartSep 2023
CompletionOct 2026
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B24024
Asset typeTrans - Roadway
Community areaOLD TOWN SAN DIEGO, UPTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)2, 3
DescriptionRepave approximately 4,842 Linear feet (0.92 miles) of street surface by asphalt concrete overlay and slurry deal. (Per work to be done on plans).
Map pieces12
Source last edited2024-01-11

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-09-11Routinecompletion date slipped ~2 months
2026-08-07Routinecompletion date nudged 13 day(s)