North Park Improv 2 (W)
San Diego · San Diego CIP
This city’s feed last changed on 2026-10-16. We check every morning.
| Status | Construction |
|---|---|
| Stage | active |
| Start | Aug 2024 |
| Completion | Feb 2027 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:B22021 |
| Asset type | Water - Distribution Sys - Distribution |
| Community area | NORTH PARK |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 3 |
| Description | This project will replace a total of approximately 12,311 linear feet (2.33 miles) of 6 and 8‐inch asbestos cement (AC) water main with appropriately sized PVC mains per water modeling. Including all |
| Map pieces | 20 |
| Source last edited | 2023-08-29 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-09 | Routine | completion date slipped ~5 weeks |
| 2026-09-11 | Routine | completion date slipped ~4 weeks |
| 2026-08-07 | Routine | completion date slipped ~5 weeks |