Construction Project Update

Midway District Improv 3 (S)

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartOct 2032
CompletionOct 2033
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B23039
Asset typeWastewater - Collection Sys - Main
Community areaPENINSULA
ContactPublic Information Line
Contact phone6195334207
Council district(s)2
DescriptionRehab approximately 4,686 LF (0.89 mi) of existing 8-, 10-, 12, 15-, 16-, 18, and 20-inch vitrified clay (VC) and concrete (CP) sewer mains. New Sewer Main Replacement of approximately 841 LF (0.16 mi
Map pieces22
Source last edited2024-04-03

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-07Routinestart date nudged 3 day(s)