StatusDesign
Stagedesign
StartOct 2031
CompletionMay 2033
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B22073
Asset typeWastewater - Collection Sys - Main
Community areaOLD TOWN SAN DIEGO, MIDWAY-PACIFIC HIGHWAY
ContactPublic Information Line
Contact phone6195334207
Council district(s)2
DescriptionConstruction of 7,840.15 LF (1.48 miles) of sewer mains to replace existing Vitrified Clay (VC) & Polyvinyl Chloride (PVC), installation of 817.63 LF (0.15 miles) of new PVC, rehabilitation of 768.72
Map pieces29
Source last edited2022-09-06

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed