StatusPlanning
Stageplanned
StartOct 2033
CompletionDec 2034
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B24031
Asset typeWastewater - Collection Sys - Main
Community areaMIDWAY-PACIFIC HIGHWAY, UPTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)2, 3
DescriptionReplacement of 1,904 LF (0.36 mi) of sewer mains. Rehabilitation of 3,705 LF (0.70 mi) of sewer mains. Installation of 707 LF (0.13 mi) of new sewer mains. Abandonment of 654 LF (0.12 mi) of sewer mai
Map pieces20
Source last edited2026-01-29

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.