Hillcrest Improv 5 (W)
San Diego · San Diego CIP
This city’s feed last changed on 2026-10-16. We check every morning.
| Status | Design |
|---|---|
| Stage | design |
| Start | Feb 2029 |
| Completion | Aug 2030 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:B26012 |
| Asset type | Water - Distribution Sys - Distribution |
| Community area | UPTOWN |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 3 |
| Description | Replacement of existing AC water mains and Installation of new PVC water mains. The project also includes installation of curb ramp(s) and paving of the ROW. |
| Map pieces | 2 |
| Source last edited | 2026-01-06 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-09 | Routine | start date slipped ~6 months |
| 2026-09-11 | Routine | start date nudged 8 day(s) |
| 2026-08-07 | Routine | start date pulled earlier by ~6 weeks |