Hillcrest Improv 5 (S)
San Diego · San Diego CIP
This city’s feed last changed on 2026-10-16. We check every morning.
| Status | Design |
|---|---|
| Stage | design |
| Start | Feb 2029 |
| Completion | Aug 2030 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:B26011 |
| Asset type | Wastewater - Collection Sys - Main |
| Community area | UPTOWN |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 3 |
| Description | Replacement of existing concrete Pipe CP) and Polyvinyl Chloride (PVC)Pipe and installation of new PVC sewer mains. The project also includes abandonment of existing sewer Concrete Pipe. Replacement o |
| Map pieces | 12 |
| Source last edited | 2026-01-07 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-09 | Routine | start date slipped ~6 months |
| 2026-09-11 | Routine | start date nudged 8 day(s) |