StatusPlanning
Stageplanned
StartFeb 2032
CompletionApr 2033
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B24030
Asset typeWater - Distribution Sys - Distribution
Community areaUPTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionReplace approximately 270 linear feet (0.05 miles) of existing 4-in asbestos cement (AC) water mains with 8-in PVC mains. Replace approximately 901 linear feet (0.17 miles) of existing 6-in asbestos c
Map pieces11
Source last edited2024-10-23

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-07Routinestart date nudged 1 day(s)