Construction Project Update

Hillcrest Improv 3 (S)

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartOct 2028
CompletionOct 2030
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B22077
Asset typeWastewater - Collection Sys - Main
Community areaUPTOWN, BALBOA PARK
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionConstruction of 5,833 LF (1.10 miles) sewer mains to rpl ex (VC) & (PVC), install of 3,784 LF (0.72 miles) of new PVC, rehab of 798 LF (0.15 miles) abandon 4,565 LF (0.86 miles) of ex VC sewer. Replum
Map pieces54
Source last edited2023-05-01

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.