Hillcrest Improv 1 (S)
San Diego · San Diego CIP
This city’s feed last changed on 2026-10-16. We check every morning.
| Status | Design |
|---|---|
| Stage | design |
| Start | Apr 2030 |
| Completion | Jan 2032 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:B19033 |
| Asset type | Wastewater - Collection Sys - Main |
| Community area | UPTOWN |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 3 |
| Description | Replace approximately 7,918 linear feet (1.5 miles) of existing 6, 8 and 10 inch diameter Vitrified Clay (VC), Poly vinyl Chloride (PVC) and Concrete (CP) sewer pipes with PVC pipes. Redirect approxim |
| Map pieces | 43 |
| Source last edited | 2019-11-25 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-08-07 | Routine | start date nudged 1 day(s) |