StatusPost Construction
Stagecomplete
StartAug 2023
CompletionMar 2026
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B22127
Asset typeDrainage - Storm Drain Pipes
Community areaUPTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionThe project will install a new drainage system that includes 18” reinforced concrete storm drain pipe, brow ditches, 60 linear feet of retaining walls, concrete pavement for drainage conveyance and as
Map pieces7
Source last edited2024-04-17