| Status | Design |
|---|---|
| Stage | design |
| Start | Feb 2029 |
| Completion | Feb 2030 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:B24104 |
| Asset type | Water - Distribution Sys - Distribution |
| Community area | BARRIO LOGAN |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 8 |
| Description | This project will replace and connect the existing 12-inch PVC to the 12-inch AC main (approximately 35 linear feet), with jump over the existing 20-inch RCSC at the intersection of Boston Av. and Sou |
| Map pieces | 1 |
| Source last edited | 2025-04-08 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-09 | Routine | completion date slipped ~1.8 years |
| 2026-08-07 | Routine | completion date moved earlier (2028-07-26 -> 2028-04-21) |