StatusPost Construction
Stagecomplete
StartAug 2021
CompletionJan 2025
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B17140
Asset typeWater - Distribution Sys - Distribution
Community areaBALBOA PARK
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionReplacement and installation of approximately 1.92 miles of existing water mains in council district 3, Balboa Park community.
Map pieces50
Source last edited2019-11-25