Balboa Park Pipeline Repl Ph III (S)

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusConstruction
Stageactive
StartApr 2021
CompletionOct 2026
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B17134
Asset typeWastewater - Collection Sys - Main
Community areaBALBOA PARK, GREATER GOLDEN HILL
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionReplace 626 LF of VC and 650 LF of CI, realign 1,295 LF of VC, rehabilitate 405 LF of VC, abandon 731 LF of VC and 526 LF of CI, including associated sewer laterals, manholes, curb ramps, etc
Map pieces3
Source last edited2019-11-25

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinecompletion date slipped ~2 months
2026-09-11Routinecompletion date nudged 4 day(s)