Asphalt Overlay Group 2111

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusPost Construction
Stagecomplete
StartAug 2022
CompletionJul 2026
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B21090
Asset typeTrans - Roadway
Community areaMID-CITY:CITY HEIGHTS, UPTOWN, NORTH PARK, GREATER GOLDEN HILL, MID-CITY:EASTERN AREA
ContactPublic Information Line
Contact phone6195334207
Council district(s)3, 9
DescriptionThe project will overlay 8.37 miles of pavement, including curb ramps, cross gutters, and subgrade repairs within the project area. The project is located within various locations throughout the City
Map pieces84
Source last edited2023-08-15

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Major29 projects: project marked complete
2026-08-07Routinecompletion date pulled earlier by ~3 weeks