Construction Project Update

Ash Street Signal Mods

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusConstruction
Stageactive
StartFeb 2024
CompletionMar 2027
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B18069
Asset typeTrans - Signals - Traffic Signals
Community areaDOWNTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionTo improve safety through the provision of traffic signal modifications, associated improvements and by addressing accessibility needs at the intersections of 1st Avenue & Ash Street, 4th Avenue & Ash
Map pieces3
Source last edited2024-05-10

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinecompletion date slipped ~2 months
2026-09-11Routinecompletion date slipped ~4 weeks
2026-08-07Routinecompletion date slipped ~5 weeks