Construction Project Update

AC Water & Sewer Group 1033 (W)

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartSep 2027
CompletionNov 2029
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B18021
Asset typeWater - Distribution Sys - Distribution
Community areaDOWNTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionReplacement of approximately 4.01 miles of existing water and 2.48 miles of existing sewer mains. The project is located in Council District 3, Downtown Community.
Map pieces24
Source last edited2025-04-04

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinestart date slipped ~2 months
2026-09-11Routinestart date nudged 2 day(s)
2026-08-07Routinestart date moved earlier (2028-07-10 -> 2027-08-03)