StatusDesign
Stagedesign
StartNov 2027
CompletionAug 2028
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B20142
Asset typeTrans - Signals - Calming/Speed Abatemt
Community areaUPTOWN, BALBOA PARK
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionDesign and construct a roundabout at the intersection of 6th Avenue and Juniper Street. Improvements include installation of traffic circle with truck apron, splitter island with passageways, curb ext
Map pieces1
Source last edited2024-05-10

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinestart date slipped ~5 weeks
2026-09-11Routinestart date slipped ~4 weeks
2026-08-07Routinestart date slipped ~5 weeks