5th and Brookes SD Upgrade
San Diego · San Diego CIP
This city’s feed last changed on 2026-10-16. We check every morning.
| Status | Construction |
|---|---|
| Stage | active |
| Start | Apr 2025 |
| Completion | Nov 2026 |
| City | San Diego |
| Source | San Diego CIP |
| Source ID | san_diego_cip:B19073 |
| Asset type | Drainage - Storm Drain Pipes |
| Community area | UPTOWN |
| Contact | Public Information Line |
| Contact phone | 6195334207 |
| Council district(s) | 3 |
| Description | This project will construct a new storm drainage system on 5th Ave from Pennsylvania Ave southerly towards Brookes Ave. The project includes the abandonment of the exist drainage system at the interse |
| Map pieces | 30 |
| Source last edited | 2021-02-03 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-11 | Routine | completion date pulled earlier by ~6 weeks |
| 2026-08-07 | Routine | completion date nudged 11 day(s) |