StatusConstruction
Stageactive
StartOct 2024
CompletionOct 2026
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B18141
Asset typeTrans - Roadway
Community areaSOUTHEASTERN SAN DIEGO
ContactPublic Information Line
Contact phone6195334207
Council district(s)9
DescriptionThis project consists of curb ramp installations, street resurfacing (overlay and/or slurry seal), and other work as pertinent and necessary to the construction of the 32nd St PH I (Market-Imp.) Under
Map pieces25
Source last edited2019-11-25

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Routinecompletion date slipped ~5 weeks