StatusPost Construction
Stagecomplete
StartAug 2024
CompletionJul 2025
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B15014
Asset typeTrans - Signals - Traffic Signals
Community areaSOUTHEASTERN SAN DIEGO
ContactPublic Information Line
Contact phone6195334207
Council district(s)9
DescriptionFully operational traffic signal. Design & construction will be needed for 31st Street & Market Street.
Map pieces1
Source last edited2024-05-10

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-09Major29 projects: project marked complete
2026-09-11Routinecompletion date slipped ~4 weeks
2026-08-07Routinecompletion date slipped ~4 weeks