Construction Project Update

1st Ave at Brookes Ave SD SWD

San Diego · San Diego CIP

This city’s feed last changed on 2026-10-16. We check every morning.

StatusDesign
Stagedesign
StartJun 2028
CompletionNov 2028
CitySan Diego
SourceSan Diego CIP
Source IDsan_diego_cip:B24023
Asset typeDrainage - Storm Drain Pipes
Community areaUPTOWN
ContactPublic Information Line
Contact phone6195334207
Council district(s)3
DescriptionThis project will be replacing Corrugated Metal Pipe (CMP) storm drains at 1st Avenue and Brookes Avenue. The pipes will be replaced and realigned with appropriately sized Reinforced Concrete Pipe (RC
Map pieces6
Source last edited2024-06-12

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-09-11Routinestart date slipped ~7 months
2026-08-07Routinestart date slipped ~4 months