Construction Project Update

Urgent Southwest Portland Sewer Rehab

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartSep 2026
CompletionDec 2026
Budget$1,500,000
CityPortland
SourcePortland CIP
Source IDportland_cip:E11714
Budget confidenceOptimal
BureauBES
ContactCommunity Outreach Hotline 503-865-4300
DescriptionAddress urgent repairs to stabilize combined sewers in the across SW Portland. Work consists of CIPP and spot repairs. 6 sewer mains.
Geometryline
Map pieces1
ProgramT03 Maint & Reliability

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-10-09Majorcompletion date slipped ~2 months
2026-10-07Majorconstruction started
2026-09-07Notablestart date slipped ~2 weeks