Construction Project Update

Transit Mall Paving & Ramps, NW/SW

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Project Development
Stagedesign
StartJan 2028
CompletionOct 2029
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:T01654
BureauPDT
ContactMatt Kelly, 503-823-5831, matthew.kelly@portlandor
Current FY budget0
DescriptionPaving reconstruction, pole repainting, curb ramp rebuilds, and red MMA markings. Design in 2026-27; construction is planned for 2028 and potentially into future years. T01654 is a non-chargeable code
Design complete (est.)2027-09-27
Design start (est.)2026-11-10
Geometryline
Map pieces1
Next FY request0
Source planRose Lanes/Enhanced Transit Corridor

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-23added
2026-10-23Routinenew design-stage project appeared