Tanner Trunk WZ04

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartApr 2026
CompletionJan 2027
Budget$7,922,486
CityPortland
SourcePortland CIP
Source IDportland_cip:E11711
Budget confidenceOptimal
BureauBES
ContactCommunity Outreach Hotline 503-865-4300
DescriptionConstruct 940' of 42" PVC sewer, 100' of 12" CIPP, 100' of 12" PVC. Work requires additional paving and 5+ ADA ramps.
Design complete (est.)2026-02-26
Geometryline
Map pieces1
ProgramT03 Maint & Reliability