StatusACTIVE · Construction
Stageactive
StartAug 2026
CompletionMay 2027
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W03178
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget250000
DescriptionThis project will install approximately 600-feet of 8-inch DI main. Abandon the existing SW Gale Avenue N of Mt Adams Drive regulator vault and assembly. Abandon approximately 150-feet of 6-inch CI ma
Design complete (est.)2026-08-31
Design start (est.)2025-06-17
Funding sourceBOND REIMBURSABLE
Geometryline
Map pieces1
Next FY request5000
Previous FY budget301501
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinebudget cut 100% ($270,986 -> $0)
2026-07-29Notablestart date slipped ~5 weeks