SW Fairmount Blvd Landslide Response
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Construction |
|---|---|
| Stage | active |
| Start | Aug 2026 |
| Completion | Sep 2026 |
| Budget | Not published |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:T01581 |
| Bureau | PDT |
| Contact | David Amiton, (503) 823-8545, david.amiton@portlan |
| Current FY budget | 0 |
| Description | Landslide response including slope stabilization and restoring the ROW for transportation uses. Design, engineering, and construction in 2026. |
| Design complete (est.) | 2026-08-18 |
| Design start (est.) | 2026-08-13 |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 0 |
| Source plan | Community Request |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-21 | Major | construction started |
| 2026-08-26 | Routine | start date nudged 3 day(s) |
| 2026-08-10 | Notable | start date slipped ~4 weeks |
| 2026-08-03 | Routine | start date nudged 10 day(s) |
| 2026-07-27 | Routine | start date nudged 3 day(s) |