SW Fairmount Blvd and 18th Dr
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Design |
|---|---|
| Stage | design |
| Start | Mar 2028 |
| Completion | Nov 2029 |
| Budget | Not published |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:W02541 |
| Budget confidence | Moderate |
| Bureau | WTR |
| Contact | Community Outreach Helpline 503-823-0102 |
| Current FY budget | 0 |
| Description | This project will install 2,000 feet of 12-inch ductile iron (DI) main and 110 feet of 4-inch DI main. The project will also transfer ten (10) services, and while seven (7) services will be renewed. A |
| Design complete (est.) | 2028-03-24 |
| Design start (est.) | 2020-12-07 |
| Funding source | BOND REIMBURSABLE |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 500000 |
| Previous FY budget | 2219715 |
| Program | Distribution |
| Status detail | 030 Design |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-12 | Major | budget cut 100% ($2,219,566 -> $0) |
| 2026-07-29 | Notable | start date slipped ~2 months |