SW College W of SW 16th Ave
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Design |
|---|---|
| Stage | design |
| Start | Nov 2026 |
| Completion | Mar 2027 |
| Budget | $369,915 |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:E11593 |
| Budget confidence | Moderate |
| Bureau | BES |
| Contact | Community Outreach Hotline 503-865-4300 |
| Description | Sanitary sewer extension in SW College St. west of SW 16th Ave. Project provided conforming sanitary service for 1628 & 1633 SW College that have private lines in the ROW. |
| Design start (est.) | 2023-08-14 |
| Geometry | line |
| Map pieces | 1 |
| Program | T03 Maint & Reliability |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-07 | Notable | start date slipped ~3 weeks |
| 2026-07-31 | Notable | start date slipped ~3 weeks |