SW Altadena Ave and Washouga Ave
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Construction |
|---|---|
| Stage | active |
| Start | Jan 2026 |
| Completion | Oct 2026 |
| Budget | Not published |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:W02511 |
| Budget confidence | High |
| Bureau | WTR |
| Contact | Community Outreach Helpline 503-823-0102 |
| Current FY budget | 316000 |
| Description | This project will install approximately 650 feet of 6-inch ductile iron main ,abandon approximately 650 feet of 6-inch cast iron (CI) main, renew thirteen (13) services, and install one (1) new hydran |
| Design complete (est.) | 2026-01-26 |
| Design start (est.) | 2019-07-18 |
| Funding source | BOND REIMBURSABLE |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 5000 |
| Previous FY budget | 379161 |
| Program | Distribution |
| Status detail | 040 Construction/Implementatio |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-12 | Routine | budget cut 100% ($362,590 -> $0) |
| 2026-07-29 | Major | completion date slipped ~2 months |