Steele Traffic Calming, 28th to 41st, SE
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Construction |
|---|---|
| Stage | active |
| Start | Oct 2026 |
| Completion | Nov 2026 |
| Budget | $142,000 |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:T01508 |
| Bureau | PDT |
| Contact | Ashley Lopez, 503-823-8093, Ashley.Lopez@portlando |
| Current FY budget | 0 |
| Description | bumps, signs |
| Design complete (est.) | 2026-09-24 |
| Design start (est.) | 2025-07-01 |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 0 |
| Source plan | 823-SAFE |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-12 | Major | construction started |
| 2026-09-14 | Notable | start date slipped ~2 weeks |
| 2026-08-03 | Notable | start date slipped ~2 months |