SE Milwaukie Ave from Gideon to Woodward
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Design |
|---|---|
| Stage | design |
| Start | Jun 2027 |
| Completion | Jun 2028 |
| Budget | Not published |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:W02499 |
| Budget confidence | Low |
| Bureau | WTR |
| Contact | Community Outreach Helpline 503-823-0102 |
| Current FY budget | 152000 |
| Description | This project will install approximately 410 feet of 8-inch ductile iron (DI) main and abandon approximately 410 ft of 10-inch CI main. Also, renew 3 existing services and transfer one hydrant. |
| Design complete (est.) | 2027-06-14 |
| Design start (est.) | 2019-07-03 |
| Funding source | BOND REIMBURSABLE |
| Geometry | line |
| Map pieces | 2 |
| Next FY request | 5000 |
| Previous FY budget | 198943 |
| Program | Distribution |
| Status detail | 030 Design |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-12 | Routine | budget cut 100% ($198,455 -> $0) |
| 2026-07-29 | Notable | start date slipped ~2 months |