Construction Project Update

SE 25th Ave from SE Salmon to DE

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartOct 2026
CompletionJul 2027
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W03118
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget110000
DescriptionThis project will install approximately 140 feet of 4-inch ductile iron (DI) main in SE 25th Ave from SE Salmon Street to the dead-end. It will abandon approximately 140 feet of 2-inch galvanized main
Design complete (est.)2026-10-05
Design start (est.)2024-10-30
Funding sourceBOND REIMBURSABLE
Geometryline
Map pieces1
Next FY request5000
Previous FY budget126913
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinebudget cut 100% ($134,656 -> $0)
2026-07-29Notablestart date pulled earlier by ~3 weeks