S Boundary St to SW View Point
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Design |
|---|---|
| Stage | design |
| Start | Nov 2026 |
| Completion | Jul 2027 |
| Budget | Not published |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:W03185 |
| Budget confidence | Low |
| Bureau | WTR |
| Contact | Community Outreach Helpline 503-823-0102 |
| Current FY budget | 105000 |
| Description | This project to install approximately 250 feet of 8-inch ductile iron (DI) main. Install three (3) valves. No services or hydrants will be installed. No main will be abandoned. |
| Design complete (est.) | 2026-11-02 |
| Design start (est.) | 2025-09-11 |
| Funding source | BOND REIMBURSABLE |
| Geometry | line |
| Map pieces | 1 |
| Previous FY budget | 124181 |
| Program | Distribution |
| Status detail | 030 Design |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-12 | Routine | budget cut 100% ($137,000 -> $0) |
| 2026-07-29 | Notable | start date slipped ~2 months |