Construction Project Update

Pride and Darcelle XV Street Plaza Improvements, SW

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartJul 2025
CompletionMay 2027
Budget$1,840,693
CityPortland
SourcePortland CIP
Source IDportland_cip:T01288
BureauPDT
ContactMatt Kelly, 503-823-5831, matthew.kelly@portlandor
Current FY budget0
DescriptionProject will improve or enhance public street plazas in the West End area of downtown and Goose Hollow. Streamlined design with no 60% milestone. Project components to include street furniture, surfac
Design complete (est.)2026-05-05
Design start (est.)2023-09-19
Geometryline
Map pieces1
Next FY request0

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-09-04Majorcompletion date slipped ~5 months
2026-08-17Majorstart date slipped ~2.0 years