Pride and Darcelle XV Street Plaza Improvements, SW
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Construction |
|---|---|
| Stage | active |
| Start | Jul 2025 |
| Completion | May 2027 |
| Budget | $1,840,693 |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:T01288 |
| Bureau | PDT |
| Contact | Matt Kelly, 503-823-5831, matthew.kelly@portlandor |
| Current FY budget | 0 |
| Description | Project will improve or enhance public street plazas in the West End area of downtown and Goose Hollow. Streamlined design with no 60% milestone. Project components to include street furniture, surfac |
| Design complete (est.) | 2026-05-05 |
| Design start (est.) | 2023-09-19 |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 0 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-04 | Major | completion date slipped ~5 months |
| 2026-08-17 | Major | start date slipped ~2.0 years |