NE Mason St from 26th to 29th Ave

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartOct 2025
CompletionNov 2026
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W03191
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget42000
DescriptionThis project will install approximately 780 feet of 6-inch ductile iron (DI) main. Also abandon approximately 430 feet of 2-inch galvanized and renew eight (8) existing services. Zero (0) hydrants wil
Design complete (est.)2025-10-13
Design start (est.)2025-09-15
Funding sourceBOND REIMBURSABLE
Geometryline
Map pieces1
Previous FY budget315699
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinebudget cut 100% ($223,000 -> $0)
2026-07-29Majorcompletion date slipped ~2 months