NE Lawrence Ave from Buxton to Hoyt

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartApr 2025
CompletionNov 2026
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W02974
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
DescriptionThis project will install approximately 260-feet of 6-inch ductile iron main. This will abandon approximately 125-feet of 2-inch galvanized main. Two (2) services will be renewed. No hydrants will be
Design complete (est.)2025-04-28
Design start (est.)2023-09-25
Funding sourceBOND REIMBURSABLE
Geometryline
Map pieces1
Previous FY budget173713
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinecompletion date slipped ~3 months
2026-07-29Majorcompletion date slipped ~2 months