N Webster St from Missouri to Michigan

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartDec 2025
CompletionDec 2026
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W03144
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget21000
DescriptionThis project will install approximately 260 feet of 6-inch ductile iron (DI) main. It will abandon approximately 100 feet of 2-inch galvanized main, renew two (2) services, and transfer one (1) servic
Design complete (est.)2025-12-17
Design start (est.)2025-02-20
Funding sourceBOND REIMBURSABLE
Geometryline
Map pieces1
Next FY request95000
Previous FY budget136265
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinebudget cut 100% ($113,520 -> $0)
2026-07-29Majorcompletion date slipped ~2 months