Morrison concrete separators, 12th to Grand, SE
Portland · Portland CIP
This city’s feed has changed within the last week. We check every morning.
| Status | ACTIVE · Engineering & Design |
|---|---|
| Stage | design |
| Start | Oct 2026 |
| Completion | Nov 2026 |
| Budget | $230,000 |
| City | Portland |
| Source | Portland CIP |
| Source ID | portland_cip:T01477 |
| Bureau | PDT |
| Current FY budget | 0 |
| Description | Replacing plastic separators with concrete separators. |
| Design complete (est.) | 2026-09-14 |
| Design start (est.) | 2025-10-10 |
| Geometry | line |
| Map pieces | 1 |
| Next FY request | 0 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
Nothing since we started tracking this project. We check every morning.