Construction Project Update

MEOC: Grate Removal at ABY517

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartJul 2026
CompletionSep 2026
Budget$50,000
CityPortland
SourcePortland CIP
Source IDportland_cip:E11828
Budget confidenceOptimal
BureauBES
ContactCommunity Outreach Hotline 503-865-4300
DescriptionGrate removal to facilitate CIP project scanning
Geometrypt
Map pieces1
ProgramT03 Maint & Reliability

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-08-03Notablebudget set ($50,000)
2026-07-31added
2026-07-31Notablenew project appeared already under construction