StatusACTIVE · Project Development
Stagedesign
StartJul 2026
CompletionDec 2026
Budget$50,000
CityPortland
SourcePortland CIP
Source IDportland_cip:T01595
BureauPDT
ContactScott Cohen, 503-823-5345, scott.cohen@portlandore
Current FY budget0
DescriptionInstall signal queue jump improvements to separate streetcar and general vehicle movements.
Design complete (est.)2026-07-27
Design start (est.)2026-04-30
Geometrypt
Map pieces1
Next FY request0
Previous FY budget0
Source plan823-SAFE, Rose Lanes/Enhanced Transit Corridor

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-17Notablebudget set ($50,000)