Interstate EV Charging Station

Portland · Portland CIP

This city’s feed has changed within the last week. We check every morning.

StatusACTIVE · Construction
Stageactive
StartJun 2025
CompletionOct 2026
BudgetNot published
CityPortland
SourcePortland CIP
Source IDportland_cip:W02745
Budget confidenceHigh
BureauWTR
ContactCommunity Outreach Helpline 503-823-0102
Current FY budget131000
DescriptionThis project will install 24 Electric Vehicle charging stations, including transformer, new electrical service and distribution equipment.
Design complete (est.)2025-06-24
Design start (est.)2021-07-26
Funding sourceBOND REIMBURSABLE
Geometrypt
Map pieces1
Previous FY budget400910
ProgramDistribution
Status detail040 Construction/Implementatio

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-12Routinecompletion date pulled earlier by ~6 months
2026-07-29Majorbudget raised 45% ($290,203 -> $421,203)